South Hook LNG Terminal Facilities

South Hook LNG Terminal Facilities

The Terminal facilities comprise of:

  • Jetty and Unloading Facilities
    Two berths to unload LNG tankers of sizes between 125,000m3 and 267,000m3;
  • LNG Tanks for Temporary Storage
    Five (5) storage tanks with a working capacity of 155,000m3 each;
  • Submerged Combustion Vaporisers (SCVs)
    A total of fifteen (15) SCVs are installed to support a firm daily Redelivery Capacity equivalent to 15.6 million metric tons per annum [MTPA] lean LNG totalling, equivalent to 21 billion cubic meters per annum [bcma] gas.
  • Nitrogen Plant
    The rate of nitrogen ballasting capacity may limit the Redelivery Capacity rate that can be achieved.    Nitrogen ballasting facilities have been designed and constructed on the assumption lean LNG produced in Qatar will be delivered at the Terminal.

 

This is produced as a guide only. The full terms and conditions for Secondary terminal capacity in the South Hook LNG Terminal are not set out in this document but will be accessible to Additional Users as set out herein. South Hook LNG Terminal Company Ltd expressly excludes any liability on its part arising from reliance upon statements in this guidance document by Additional Users. This guidance document is subject to change from time to time.